Gilead Building 800

Gilead Building 800 Contract Amount: $21,000,000 Start / Completion Date: October 2015 / June 2017 Design-assist of a 214,000 sf lab/office project with GMP warehouse and a full cafeteria. In addition to the common lab services, this project included GMP clean areas, a WFI system, clean steam, a validated purified water system, LN2, industrial waste [...]
2

Illumina B6

Illumina B6 Contract Amount: $24,000,000 Start / Completion Date: January 2015 / July 2016 Design-assist of 275,000 sf ground-up campus manufacturing/lab/office building. Scope included HVAC, plumbing and process piping for the building including 50,000 sf of manufacturing space. Project also included the addition of 1,600 tons of capacity to the existing campus central plant. Recent [...]